Skip to content

Job costing for contractors: the report can only add up the costs you recorded

Job costing for contractors: the report can only add up the costs you recorded

Job costing is adding up everything a single job cost you, the technician’s hours, the labor burden on those hours, the parts, the equipment and anything bought for that job, and setting the total against what the job billed. What is left is the job’s gross margin. The arithmetic takes a minute. The trouble is the cost that never got recorded, because a report can only subtract the numbers somebody entered. To get your own number, use the free loaded labor rate calculator.

What job costing measures

Think of every job as its own small profit and loss statement. Revenue is the invoice subtotal before tax. Against it sit four kinds of cost:

  • What you paid the tech for the hours on that job.
  • The labor burden, what each hour costs you on top of pay: payroll taxes, insurance, benefits, fuel and the rest of the overhead that follows a tech around.
  • The parts and units that went into the job, at your cost.
  • Other purchases for that job, excluding costs already counted above.

Count each cost once, even if the same part appears on both an invoice and a purchasing record. Gross margin is revenue minus those costs. Divide it by revenue and you have the job’s margin percentage, the number that tells you whether this kind of work pays.

A worked example, with made-up numbers. A repair bills $600. The tech spends 3 hours on it at a burdened rate of $50 an hour, and the job uses $120 of parts. Cost is $150 plus $120, so $270. The job’s gross margin is $330, which is 55%.

That $330 is not the owner’s profit or cash in the bank. Office costs, marketing, financing charges and other expenses still have to be covered if they were not allocated to this job. An invoice also is not a payment: the customer may not have paid yet. Do not subtract a cost again if the burden rate or another job-cost line already includes it.

That $50 is not pulled from the air. ServiceTitan’s own help center uses it as its burden example: $30,000 of overhead plus $70,000 of payroll over 2,000 hours worked comes to $50 an hour. That example includes payroll. If ServiceTitan already includes labor pay separately in job costing, exclude that payroll from the technician’s burden rate to avoid counting wages twice. Our guide to the loaded labor rate builds a rate for pricing; do not copy it into a technician’s costing settings without checking what those settings include.

Same job, two margins. One counts every cost. One counts what was entered. What the job cost labor pay burden parts other cost margin What the report saw labor pay margin, mostly costs nobody entered Schematic. Each cost is counted once. Every unrecorded cost shows up as margin that is not there.

Expected parts are not actual job usage

The materials and quantities linked to a service describe what you expect the work to require. They give you a consistent starting point for a flat-rate price. With static pricing, someone sets that selling price; with dynamic pricing, ServiceTitan calculates it from the service’s pricing inputs and rules.

Job costing answers a different question: what did this particular job actually use and cost? A tech may use a different part or quantity. Record those differences through the invoice, purchasing and inventory workflows your account uses, rather than assuming the pricebook’s default quantities match every job.

Depending on your costing configuration, the invoice can be a cost source. ServiceTitan lets you record consumed quantities and their inventory location on it. But purchasing can carry the cost instead. Costing settings determine how purchase orders, receipts and vendor bills feed the calculation. Where a purchase is already costed, its invoice item can intentionally have $0 cost to prevent duplication.

Recording actual usage does not necessarily change the customer’s price. ServiceTitan documents that editing or deleting equipment lines does not automatically recalculate a dynamic service price. Keep the selling price, expected cost and recorded job cost separate when you review the margin.

Where the cost goes missing

The report is honest. It adds what it was given. So a margin that looks too good usually means one of these is empty:

  1. Materials whose use or cost was never recorded. One plumbing account we looked at had roughly 43,000 materials in its pricebook and almost none linked to the services that use them. That left expected parts dependent on manual entry or another workflow. Missing links alone do not prove missing job costs: check the actual invoice, purchasing and inventory records. We did not measure that shop’s actual margins.
  2. A burden rate of zero. If a technician record has no burden rate, or a leftover default, every hour he works costs the report less than it costs you.
  3. Purchases never assigned to the job. A supply house run on a card, with no cost recorded against the job, leaves the report short. A job PO is one route; a job-linked vendor bill can be another, depending on the setup.
  4. Work keyed as “miscellaneous” without the costs behind it. We have seen whole installs billed on a miscellaneous labor line. The selling price alone does not record the parts used; check whether those costs were captured elsewhere before treating the job as costed.

Job costing in ServiceTitan

On accounts using ServiceTitan’s legacy job-costing workflow, open an invoice and pick Job Costing from the invoice menu, and the tool breaks the job into labor pay, labor burden, materials, purchase orders and equipment, each with its share of revenue, and a gross margin at the bottom. For many jobs at once, build a report from the Jobs template and add the cost columns. Each technician’s burden rate lives under Settings, People, Technicians, in the Revenue & Cost section of his record.

If your account uses GL-Based Costing, Job Financials replaces that legacy view. Costs follow journal entries: non-inventory invoice materials need a purchase order with a receipt or bill to produce job costs, while consumed inventory still produces cost. Confirm which workflow your account uses before diagnosing a missing amount.

The tool is only as good as the costs behind it. Linking materials reduces manual entry and gives the service a consistent parts list. It does not replace checking actual usage or the account’s costing workflow. On commercial time-and-materials work it matters even more, which the commercial pricebook guide covers.

A completed job can still have unfinished costs

A tech marking the work complete does not mean every cost has reached the report. In ServiceTitan’s legacy Job Costing tool, configured performance pay appears only after the invoice is posted. Purchasing costs depend on your costing settings: purchase orders, receipts and vendor bills enter at different stages. Check those records before treating the margin as final; an early report can look better simply because a cost has not arrived yet.

A first pass you can do this week

  1. Pull your last ten completed jobs, then confirm the relevant invoice, payroll and purchasing records are ready for costing. Mark any unfinished costs before comparing margins.
  2. Compare the expected parts with what was actually used. Trace each cost through invoice materials, job purchasing records and the inventory workflow. A $0 invoice cost can be correct if the cost is captured elsewhere; a missing cost or a duplicate is the gap.
  3. Open your technician records and confirm every tech has a burden rate that matches your own math.
  4. Compare expected and recorded job margin. Where they disagree, check quantities used, cost sources, missing costs and duplicates.

Gross margin is one of the four numbers worth checking every Monday, and it is only worth checking once the costs are in. If you want the setup done for you, our ServiceTitan consulting covers job costing and contractor bookkeeping, and the free Pricebook Health Audit shows which services in your export carry no linked parts. When the book itself is the gap, that is the pricebook work we do.

FAQ

What is job costing?

Job costing is adding up everything one job cost you, technician pay for the hours, labor burden, materials, equipment and other job costs, each counted once, and setting the total against what the job billed. The difference is the job’s gross margin, and gross margin divided by revenue is its margin percentage.

How do you calculate job costing for a contractor?

Take the invoice subtotal before tax as revenue. Add the cost of the hours (pay plus burden), the parts and equipment actually used, and other job costs. Count each cost once: do not add a purchase again if its cost is already included through the invoice or inventory workflow. Revenue minus that total is gross margin. Example with made-up numbers: a $600 job, 3 hours at a $50 burdened rate and $120 of parts costs $270, so its gross margin is $330, or 55%, before costs not allocated to this job. That is not owner profit or cash collected.

Why does my job costing show a margin that is too high?

Missing costs can make the margin read too high. Check actual material usage, labor and burden, and purchases assigned to the job. A $0 material line is not proof of missing cost: the cost may already be recorded through purchasing or inventory. Check your account’s costing settings and count each cost once.

← All field notes

Want this done, or want to do it yourself?

We rebuild ServiceTitan pricebooks for HVAC, plumbing and electrical shops. Or run your own export through the free tools and see what is in it.

Built for HVAC, plumbing and electrical shops running on ServiceTitan.